AllSecure System - UniCredit Bank Planned Maintenance Activities: Disaster Recovery Exercise – Maintenance details
All systems operational
UniCredit Bank Planned Maintenance Activities: Disaster Recovery Exercise
Completed
Scheduled for 27/09/2023 at 22:30:00 – 28/09/2023 at 00:30:00
Affects
OPEN PLATFORM
Under maintenance from 10:30 PM to 12:30 AM
Updates
Completed
28/09/2023 at 00:30:00
Completed
28/09/2023 at 00:30:00
Maintenance has completed successfully
In progress
27/09/2023 at 22:30:01
In progress
27/09/2023 at 22:30:01
Maintenance is now in progress
Planned
27/09/2023 at 22:30:00
Planned
27/09/2023 at 22:30:00
Please be informed about planned system maintenance - the following maintenance activity to be performed by UniCredit bank acquiring processor related to Disaster Recovery exercise, switching from primary datacenter to secondary (backup). All responsible teams will be closely monitoring the situation with immediate intervention in case of any anomalies.
Time Start: 28/09/2023 00:30 AM (CET)
Time End: 28/09/2023 02:30 AM (CET)
Description: UniCredit bank acquiring processor will perform Disaster Recovery exercise.
Impact: The processor expects 30 minutes authorization outage in timeframe mentioned above.
Affected Services: UniCredit Bank processing services